3/14/20 - The original state of the boat.
3/16/20 - The deck panels are epoxied together.
3/17/20 - The deck is wired up.
3/18/20 - The deck seams are filled with epoxy.
3/19/20 - The deck is removed and flipped.
The underside of the deck is reinforced with fiberglass tape and sealed with epoxy.
3/23/20 - Fiberglass cloth is laid out on the interior.
The cloth has been saturated with epoxy.
3/24/20 - One side of footbrace studs are installed.
The bulkheads are ready for fiberglass.
Recessed deck fittings are fabricated.
3/30/20 - The deck is fit to the hull.
The sheer joint is filled with epoxy.
4/1/20 - The inside of the sheer joints are filled with epoxy and fiberglass tape.
4/2/20 - Hatch lips and recessed fittings are sealed with epoxy.
4/4/20 - A thick bead of epoxy is applied to the bow.
4/6/20 - Fiberglass cloth is laid on the hull.
The cloth is saturated with epoxy.
8/8/20 - Two fill coats of epoxy are applied to the hull.
4/9/20 - Time to work on the deck.
4/10/20 - The deck is sanded.
4/13/20 - Fiberglass cloth is laid on the deck.
The fiberglass is saturated with epoxy.
The extra cloth is cut off along the tape.
4/14/20 - The glass is trimmed and fill coats or epoxy have been applied.
4/16/20 - The hatch shapes are drawn on the deck.
The hatches have been cut out.
Holes for recessed deck fittings are cut out.
Coaming riser is epoxied in place.
4/22/20 - The recessed deck fittings are fiberglassed.
The coaming lip and aft bulkhead are installed.
4/23/20 - Fiberglass cloth is laid on the coaming lip.
The glass is saturated with epoxy.
4/24/20 - The fiberglass is trimmed and an epoxy fill coat is added.
The forward hatch lip is epoxied in place.
The aft hatch lip is epoxied in place.
4/29/20 - The boat partially sanded.
4/30/20 - The hull is washed and ready for varnish.
Once coat of varnish is applied.
5/2/20 - Several coats of varnish have been applied.
5/4/20 - The deck is ready for varnish.
The deck gets the first coat of varnish.
First coat on the hatch covers.
5/5/20 - Second coat of varnish.
5/7/20 - Several coats of varnish have been applied.
5/8/20 - Deck rigging and hatch straps are installed.