8/12/21 - The box is opened.
Bulkhead and transom pieces are laid out.
One of the take apart bulkheads is epoxied together.
8/17/21 - #1 and #2 panels are wired to the bottom with the temporary bulkhead.
Take apart bolts are epoxied in place.
Daggerboard trunk is epoxied together.
8/18/21 - The hull is wired up.
9/2/21 - The joints between panels are filled with epoxy.
9/10/21 - Fillets are added to the bulkheads, transoms, and joints between bottom and #1 panels.
9/13/21 - Fiberglass cloth is laid out.
The cloth is saturated with epoxy.
The extra cloth is trimmed.
9/14/21 - The daggerboard trunk is epoxied in place.
9/27/21 - The seat supports are epoxied in place.
The two skeg halves are epoxied together.
The outboard doubler is epoxied in place.
10/1/21 - The skeg is temporarily mounted.
The undersides of the seat supports are reinforced with fillets and fiberglass tape.
Rails are epoxied in place.
10/4/21 - Fiberglass is laid on the outside of the hull.
The glass is saturated with epoxy.
The skeg is screwed and epoxied in place.
Test fitting the skids.
The skids are screwed and epoxied in place.
10/5/21 - Quarter knees are epoxied in place.
10/6/21 - It is time to saw the boat in half!
The boat is cut in half.
10/7/21 - The mast step is screwed and epoxied in place.
10/8/21 - The hole for the daggerboard is cut out.
10/11/21 - The outside of the hull is given a seat coat of epoxy.
10/14/21 - Handles for daggerboard are laminated together.
Interior of aft section is given a seal coat of epoxy.
10/20/21 - The gudgeons and pintles are temporarily mounted.
Forward oarlocks are temporarily mounted.
Aft oarlock risers are epoxied in place.
10/21/21 - The Rudder and daggerboard are shaped.
Rudder is fiberglassed and forward seat is sealed with epoxy.
10/25/21 - The hull has been sanded in preparation for primer.
10/26/21 - The hull is taped off for primer.
First coat of primer.
10/28/21 - The two coats of primer have been sanded. Ready for paint!
10/29/21 -The first coat of paint is applied.
10/30/21 - Two coats of paint.
11/1/21 - Parts are sealed with epoxy.
11/2/21 - The entire interior is given a seal coat of epoxy.
Spars are sealed with epoxy.
11/5/21 - Sanding in proparation for varnish has begun.
Spars, seats, and foils are sanded.
11/8/21 - Foam for underseat reserve floatation is epoxied together.
11/9/21 - Sanding is complete. The boat is ready for varnish.
The foam pieces are epoxied to the underside of the seats.
11/10/21 - The foam is shaped.
The foam is covered with epoxy.
11/11/21 - The foils and spars are varnished.
Foam is given another coat of epoxy.
11/12/21 - The foam blocks are sanded and painted.
11/15/21 - The first coat of varnish is applied.
Tops of the seats are varnished.
11/17/21 - The sail is rigged and the boat is complete!