Photos of the construction process.
  •  11/17/21 - The kit is unpacked.

    11/17/21 - The kit is unpacked.

  •  11/18/21 - Doublers and cleats are epoxied to the bulkheads.

    11/18/21 - Doublers and cleats are epoxied to the bulkheads.

  •  The hull panels are epoxied to full length.

    The hull panels are epoxied to full length.

  •  11/19/21 - Sheer clamps are epoxied to the inside edge of the #3 panel.

    11/19/21 - Sheer clamps are epoxied to the inside edge of the #3 panel.

  •  #1 panels are wired together and to the bulkheads.

    #1 panels are wired together and to the bulkheads.

  •  #2 panels are in place.

    #2 panels are in place.

  •  11/20/21 - The hull if fully wired together.

    11/20/21 - The hull if fully wired together.

  •  Boat is flipped and wires are tightened.

    Boat is flipped and wires are tightened.

  •  Joints between panels are filled with epoxy.

    Joints between panels are filled with epoxy.

  •  11/21/21 - The bulkheads are tack welded in place.

    11/21/21 - The bulkheads are tack welded in place.

  •  11/22/21 - All wires are pulled, bulkheads filleted and inside has been fiberglassed.

    11/22/21 - All wires are pulled, bulkheads filleted and inside has been fiberglassed.

  •  11/23/21 - The undersides of the cockpit decks are sealed with epoxy.

    11/23/21 - The undersides of the cockpit decks are sealed with epoxy.

  •  All bare wood is given a seal coat of epoxy.

    All bare wood is given a seal coat of epoxy.

  •  11/24/21 - Fiberglas cloth is laid on the hull.

    11/24/21 - Fiberglas cloth is laid on the hull.

  •  Th cloth is saturated with epoxy.

    Th cloth is saturated with epoxy.

  •  Cockpit decks are fiberglassed.

    Cockpit decks are fiberglassed.

  •  11/27/21 - A hole for an Anderson mini bailer is cut.

    11/27/21 - A hole for an Anderson mini bailer is cut.

  •  The skeg is epoxied in place.

    The skeg is epoxied in place.

  •  2/28/21 - The skeg is fiberglassed.

    2/28/21 - The skeg is fiberglassed.

  •  11/29/21 - Fiberglass is laid on the transom.

    11/29/21 - Fiberglass is laid on the transom.

  •  Saturated with epoxy.

    Saturated with epoxy.

  •  11/30/21 - A fill coat of epoxy is applied to the hull.

    11/30/21 - A fill coat of epoxy is applied to the hull.

  •  12/2/21 - Fiberglass cloth is laid on the underside of the deck.

    12/2/21 - Fiberglass cloth is laid on the underside of the deck.

  •  The cloth is saturated with epoxy.

    The cloth is saturated with epoxy.

  •  12/3/21 - Lower deck support beams are epoxied in place.

    12/3/21 - Lower deck support beams are epoxied in place.

  •  12/4/21 - The cockpit decks are test fit.

    12/4/21 - The cockpit decks are test fit.

  •  12/5/21 - Cockpit decks are epoxied in place.

    12/5/21 - Cockpit decks are epoxied in place.

  •  12/6/21 - Holes are drilled for the sliding seat.

    12/6/21 - Holes are drilled for the sliding seat.

  •  The cockpit decks are filleted.

    The cockpit decks are filleted.

  •  Overall shot of the boat.

    Overall shot of the boat.

  •  12/8/21 - Reinforcement blocks are epoxied onto the underside of the deck.

    12/8/21 - Reinforcement blocks are epoxied onto the underside of the deck.

  •  12/9/21 - The deck is epoxied in place.

    12/9/21 - The deck is epoxied in place.

  •  12/13/21 - The deck is sanded and taped off for fiberglassing.

    12/13/21 - The deck is sanded and taped off for fiberglassing.

  •  Fiberglass is laid on the deck.

    Fiberglass is laid on the deck.

  •  The glass is saturated with epoxy.

    The glass is saturated with epoxy.

  •  The excess cloth is trimmed.

    The excess cloth is trimmed.

  •  12/14/21 - A fill coat of epoxy is applied to the deck.

    12/14/21 - A fill coat of epoxy is applied to the deck.

  •  12/15/21 - The coaming is epoxied in place.

    12/15/21 - The coaming is epoxied in place.

  •  12/16/21 - Hatches are cut out.

    12/16/21 - Hatches are cut out.

  •  12/17/21 - Rub rails are epoxied and nailed in place.

    12/17/21 - Rub rails are epoxied and nailed in place.

  •  12/19/21 - The hatch lips are epoxied in place.

    12/19/21 - The hatch lips are epoxied in place.

  •  12/20/21 - All remaining bare wood is sealed with epoxy.

    12/20/21 - All remaining bare wood is sealed with epoxy.

  •  12/23/21 - The hull is partially sanded.

    12/23/21 - The hull is partially sanded.

  •  The hull is sanded in preparation for primer.

    The hull is sanded in preparation for primer.

  •  1/1/22 - The first coat of primer is applied.

    1/1/22 - The first coat of primer is applied.

  •  1/2/22 - The primer is sanded on the starboard side.

    1/2/22 - The primer is sanded on the starboard side.

  •  1/3/22 - The port side is sanded.

    1/3/22 - The port side is sanded.

  •  1/4/22 - The first coat of paint is applied to the hull.

    1/4/22 - The first coat of paint is applied to the hull.

  •  1/11/22 - The deck is sanded.

    1/11/22 - The deck is sanded.

  •  Deck and cockpit are primed.

    Deck and cockpit are primed.

  •  1/12/22 - The primer is sanded.

    1/12/22 - The primer is sanded.

  •  First coat of yellow on the deck and Seattle grey in the cockpit.

    First coat of yellow on the deck and Seattle grey in the cockpit.

  •  1/13/22 - Second coat of paint on deck and cockpit.

    1/13/22 - Second coat of paint on deck and cockpit.

  •  1/19/22 - 6 coats of yellow have been applied.

    1/19/22 - 6 coats of yellow have been applied.

  •  1/20/22 - The rubrails and coaming are painted with the first coat of black.

    1/20/22 - The rubrails and coaming are painted with the first coat of black.

  •  1/21/22 - Paintind is complete aside from a few touch ups.

    1/21/22 - Paintind is complete aside from a few touch ups.

  •  1/23/22 - The Anderson mini Self Bailer is installed.

    1/23/22 - The Anderson mini Self Bailer is installed.

  •  1/24/22 - Cleats and a mount for a navigation light are installed..

    1/24/22 - Cleats and a mount for a navigation light are installed..

  •  Piantidosi sliding seat is installed.

    Piantidosi sliding seat is installed.