11/17/21 - The kit is unpacked.
11/18/21 - Doublers and cleats are epoxied to the bulkheads.
The hull panels are epoxied to full length.
11/19/21 - Sheer clamps are epoxied to the inside edge of the #3 panel.
#1 panels are wired together and to the bulkheads.
#2 panels are in place.
11/20/21 - The hull if fully wired together.
Boat is flipped and wires are tightened.
Joints between panels are filled with epoxy.
11/21/21 - The bulkheads are tack welded in place.
11/22/21 - All wires are pulled, bulkheads filleted and inside has been fiberglassed.
11/23/21 - The undersides of the cockpit decks are sealed with epoxy.
All bare wood is given a seal coat of epoxy.
11/24/21 - Fiberglas cloth is laid on the hull.
Th cloth is saturated with epoxy.
Cockpit decks are fiberglassed.
11/27/21 - A hole for an Anderson mini bailer is cut.
The skeg is epoxied in place.
2/28/21 - The skeg is fiberglassed.
11/29/21 - Fiberglass is laid on the transom.
Saturated with epoxy.
11/30/21 - A fill coat of epoxy is applied to the hull.
12/2/21 - Fiberglass cloth is laid on the underside of the deck.
The cloth is saturated with epoxy.
12/3/21 - Lower deck support beams are epoxied in place.
12/4/21 - The cockpit decks are test fit.
12/5/21 - Cockpit decks are epoxied in place.
12/6/21 - Holes are drilled for the sliding seat.
The cockpit decks are filleted.
Overall shot of the boat.
12/8/21 - Reinforcement blocks are epoxied onto the underside of the deck.
12/9/21 - The deck is epoxied in place.
12/13/21 - The deck is sanded and taped off for fiberglassing.
Fiberglass is laid on the deck.
The glass is saturated with epoxy.
The excess cloth is trimmed.
12/14/21 - A fill coat of epoxy is applied to the deck.
12/15/21 - The coaming is epoxied in place.
12/16/21 - Hatches are cut out.
12/17/21 - Rub rails are epoxied and nailed in place.
12/19/21 - The hatch lips are epoxied in place.
12/20/21 - All remaining bare wood is sealed with epoxy.
12/23/21 - The hull is partially sanded.
The hull is sanded in preparation for primer.
1/1/22 - The first coat of primer is applied.
1/2/22 - The primer is sanded on the starboard side.
1/3/22 - The port side is sanded.
1/4/22 - The first coat of paint is applied to the hull.
1/11/22 - The deck is sanded.
Deck and cockpit are primed.
1/12/22 - The primer is sanded.
First coat of yellow on the deck and Seattle grey in the cockpit.
1/13/22 - Second coat of paint on deck and cockpit.
1/19/22 - 6 coats of yellow have been applied.
1/20/22 - The rubrails and coaming are painted with the first coat of black.
1/21/22 - Paintind is complete aside from a few touch ups.
1/23/22 - The Anderson mini Self Bailer is installed.
1/24/22 - Cleats and a mount for a navigation light are installed..
Piantidosi sliding seat is installed.