6/9/22 - The project begins.
The first few panels are epoxied together.
Bulkheads are epoxied together.
6/24/22 - The bottom and # 1 panels are wired together.
# 2 panels are wired on.
Bulkheads and transom are wired in place.
#3 panels and rest of bulkheads are wired in place.
#4 panels are wired in place.
Final panels are in place.
6/27/22 - The hull is flipped and the wires are tightened.
Seams between panels are partially filled with epoxy.
6/28/22 - Wires have been pulled and fiberglass is cut for the interior.
6/29/22 - Filletts are applied to the bulkheads and between #1 and #2 panels.
Fiberglass is unfolded and ready for epoxy.
Glass is epoxy saturated.
Excess cloth is trimmed off.
7/5/22 - The seams between panels are filled with epoxy.
7/6/22 - The hul is sanded.
7/8/22 - Fiberglass cloth is laid on the outside.
The cloth is saturated with epoxy.
Excess cloth is trimmed.
View of the stern.
7/10/22 - The skeg is epoxied in place.
7/17/22 - Skeg is filletted and brass rub strip is temporarily mounted.
7/18/22 - Port side rails are epoxied in place.
7/19/22 - Starboard side rails are installed.
Forward tank top is test fit.
Aft tank top is test fit.
Underside of tank tops are epoxy sealed.
Rudder is laminated from two pieces of wood.
7/20/22 - Forward tank top epoxied in place.
Aft tank top epoxied in place.
7/21/22 - The sliding seat is fit to the middle rowing position.
Fit to the forward postion.
7/23/22 - The rudder is mounted.
7/24/22 - Tiller arm is epoxied in place.
Wooden battens for a cover are cut to length.
7/25/22 - The interior is given first epoxy seal coat.
Rudder is given epoxy seal coat.
7/27/22 - Epoxy seal coats are applied to the hull.
7/31/22 - Parts for the queen seat are laminated together.
7/31/22 - Seat and back slats are fiberglassed.
8/17/22 - The seat is partially epoxied together.
8/29/22 - Half the hull is sanded.
9/7/22 - The seat is sanded and epoxied together.
9/12/22 - The hull is sanded and ready for primer.
Seat back slats are epoxied in place.
9/14/22 - The hull is primed.
The rudder is primed.
9/15/22 - First coat of paint on the hull bottom.
First coat on the rudder.
9/16/22 - Second coat of paint.
9/16/22 - the queen seat gets the first coat of varnish.
9/20/22 - First coat of white is applied.
Second coat of white.
9/28/22 - Tape is removed and rubstrips are attached.
Interior is partially sanded.
9/29/22 - The interior is sanded and ready for varnish.
10/3/22 - First coat of varnish is applied.
10/6/22 - After several coats of gloss epoxy a final coat of satin is applied. It stays shiny until it dries.
The queen seat has been varnished.