5/6/23 - The boat is in the workshop.
3/7/23 - The underside of the forward deck is epoxy sealed.
3/9/23 - The forward deck is epoxied and nailed in place.
Coaming is temporarily fitted.
3/11/23 - The deck overhang is trimmed.
3/12/23 - The deck is half sanded.
3/13/23 - Fiberglass cloth is laid on the deck.
The cloth is saturated with epoxy.
3/14/23 - The forward hatch is cut out.
Rims around the hatch openings are epoxied in place.
The cockpit coaming is epoxied in place.
3/15/23 - Stiffeners are epoxied to the underside of the hatch openings.
Hatch stiffeners are epoxied to the hatch lids.
Coaming is filletted.
3/16/23 - Stiffeners are filletted.
Coaming is filletted and fiberglassed.
3/17/23 - Hatch straps are temporarily mounted.
Epoxy seal coat is applied.
3/23/23 - Parts for the sliding seat are cut out.
3/27/23 - Rigger support risers are epoxied in place.
3/28/23 - The entire deck is given a seal coat of epoxy.
4/12/23 - Half of the deck is sanded in preparation for painting.
4/14/23 - The hull is sanded and washed.
4/18/23 - Primer is applied to the hull and other parts.
4/23/23 - The deck is coated with primer.
5/2/23 - First coat of paint is applied.
First coat of paint is applied to the extra parts.
5/8/23 - First coat of paint on the deck.
Cockpit.
5/11/23 - The final fit out is under way.