I am finishing this boat for a student builder from a Skerry class at the Center for Wooden Boats. She has the sprit rig sailing option.
Length: 15 feet
Beam: 54 inches
Weight: ~95 pounds
-
4/3/20 - The boat is finished!
-
CLC Skerry
-
CLC Skerry
-
11/5/19 - The project begins.
-
11/13/19 - Rudder trunk pieces are fiberglassed.
-
Skeg wormshoe is epoxied in place.
-
11/16/19 - The first seal coat of epoxy is applied to the hull.
-
11/17/19 - The second seal coat is applied.
-
11/20/19 - The hull is partially sanded.
-
The hull is sanded and ready for primer.
-
11/25/19 - The first coat of primer is sanded.
-
PVC is trimmed and sanded.
-
11/26/19 - The primer is sanded.
-
11/27/19 - The first coat of paint is appiled.
-
12/3/19 - The spars are sanded.
-
Four coats of paint are applied.
-
One seal coat of epoxy is applied.
-
Two seal coats of epoxy.
-
12/6/19 - The first seal coat of epoxy is applied to the spars.
-
Foils are fiberglassed.
-
Mahogany footbraces are sealed with epoxy.
-
12/10/19 - Seal coats of epoxy are applied.
-
Final seal coat of epoxy is applied to the spars.
-
The rudder is test mounted.
-
3/12/20 - The final coat of paint is applied to the hull.
-
3/14/20 - The foils are sanded.
-
3/17/20 - The interior is half sanded.
-
Sanding of the interior is complete.
-
3/18/20 - The interior is washed.
-
The interior is taped off in preparation for primer.
-
3/19/20 - The first coat of primer is applied to the interior.
-
3/24/20 - The final coat of paint is applied.
-
3/26/20 - The first coat of varnish is applied to the seats and bulkheads.
-
The spars get a coat of varnish.
-
Rudder and daggerboard are varnished.
-
3/27/20 - Two more coats of varnish have been applied.
-
4/1/20 - Footbraces are epoxied in place.
-
Major construction is complete!
-
Hardware is installed on mast.
-
4/2/20 - The boat is moved outside to allow for rigging the sail.
-
The sail is fit to the spars.
-
The sail rig is set up.
-
The rudder is hung on the stern.
Link to full construction gallery.
-
11/5/19 - The project begins.
-
11/12/19 - The hull seams are filled with epoxy.
-
11/13/19 - Rudder trunk pieces are fiberglassed.
-
Skeg wormshoe is epoxied in place.
-
The spars are epoxied to full length.
-
11/16/19 - The first seal coat of epoxy is applied to the hull.
-
11/17/19 - The second seal coat is applied.
-
11/20/19 - The hull is partially sanded.
-
The hull is sanded and ready for primer.
-
11/24/19 - A PVC tow eye is installed.
-
11/25/19 - The first coat of primer is sanded.
-
Second coat of primer is applied.
-
PVC is trimmed and sanded.
-
11/26/19 - The primer is sanded.
-
11/27/19 - The first coat of paint is appiled.
-
12/1/19 - The second coat of paint is on.
-
12/3/19 - The spars are sanded.
-
Four coats of paint are applied.
-
12/5/19 - Work on the interior begins!
-
One seal coat of epoxy is applied.
-
Two seal coats of epoxy.
-
12/6/19 - The first seal coat of epoxy is applied to the spars.
-
-
Foils are fiberglassed.
-
Mahogany footbraces are sealed with epoxy.
-
12/10/19 - Seal coats of epoxy are applied.
-
Final seal coat of epoxy is applied to the spars.
-
Spacers for rudder gudgeons are epoxied in place.
-
The rudder is test mounted.
-
3/11/20 - The underside of the seat/bulkhead joint is filletted.
-
3/12/20 - The final coat of paint is applied to the hull.
-
3/14/20 - The foils are sanded.
-
3/17/20 - The interior is half sanded.
-
Sanding of the interior is complete.
-
3/18/20 - The interior is washed.
-
The interior is taped off in preparation for primer.
-
3/19/20 - The first coat of primer is applied to the interior.
-
3/20/20 - The first coat of paint is applied.
-
3/23/20 - Second coat of paint is applied.
-
3/24/20 - The final coat of paint is applied.
-
3/25/20 - The tape is removed and the boat is ready for varnish.
-
3/26/20 - The first coat of varnish is applied to the seats and bulkheads.
-
The spars get a coat of varnish.
-
Rudder and daggerboard are varnished.
-
3/27/20 - Two more coats of varnish have been applied.
-
4/1/20 - Footbraces are epoxied in place.
-
Major construction is complete!
-
Hardware is installed on mast.
-
4/2/20 - The boat is moved outside to allow for rigging the sail.
-
The sail is fit to the spars.
-
The sail rig is set up.
-
The rudder is hung on the stern.